Anyone who drives the Benin-Auchi road knows the long stretches of old, narrow carriageway between Benin City, Ekpoma and Auchi. On Thursday, the Federal Government told a rally crowd in Benin City that its dualisation of the road is under way. The Benin-Auchi road project is real and has a public record. That record is thinner than the speeches suggest.
Vice-President Kashim Shettima made the promise on Thursday, 12 November 2026, at the Samuel Ogbemudia Stadium. He was standing in for President Bola Tinubu at an All Progressives Congress (APC) rally that also marked Governor Monday Okpebholo’s second year in office. The presidential election is on 16 January 2027.
What Shettima said in Benin
According to the Federal Ministry of Information, Shettima listed the dualisation of roads linking Benin with Ekpoma, Auchi and Okene, and emergency repairs on the Benin-Asaba highway. Reports in the Nigerian Tribune and P.M. News quoted him naming Okpella, the Edo town between Auchi and Okene, and the Benin-Agbor-Sapele road as well.
“We have come to assure you that you can count on us too,” he told the crowd, in words carried by the ministry and the Tribune. He said the government had kept its side of an agreement with Edo voters made four years earlier. “We have not abandoned that agreement,” he said.
Okpebholo, for his part, told the rally that salaries and pensions were being paid while construction went on across the state, according to the Tribune and P.M. News. He promised Tinubu 2.5 million Edo votes.
The Benin-Auchi road record so far
The road Shettima described is the federal highway from Ajaokuta Junction in Kogi State through Okene, Okpella, Auchi and Ekpoma to Benin. The Ministry of Works splits it into four sections.
On Wednesday, 19 February 2025, Works Minister David Umahi flagged off three of them at Ekpoma, representing the President. A ministry statement signed by its press director, Mohammed Ahmed, said the earlier contracts for sections II, III and IV had been terminated “due to non-performance and effluxion of time” and then re-awarded. Effluxion of time is a legal phrase. It means the contract period simply ran out.
The statement gave these sections and firms:
- Section I, Obajana Junction to Ajaokuta Junction: already under way, CGC Nigeria Ltd.
- Section II, Okene to Auchi: about 63.7 km, CGC Nigeria Ltd.
- Section III, Auchi to Ehor: about 54.2 km, BUA Construction Nigeria Ltd.
- Section IV, Ehor to Benin: about 67.9 km, CBC Nigeria Ltd.

Our sum of the three re-awarded sections comes to about 185.8 km. Sections III and IV, which lie wholly in Edo State, cover about 122.1 km between Auchi and Benin. The ministry said three of the four sections fall within Edo.
The ministry also said the road would be rebuilt with continuously reinforced concrete pavement, a type of rigid concrete road surface. It claimed a guarantee of 50 to 100 years. At the Ekpoma ceremony, Okpebholo said the new road would have three lanes. “As someone who resides along this corridor, I understand the pains of the people,” he said.
What the public record does not show
De Auditor Space checked the ministry’s flag-off statement, the reports of the February 2025 ceremony, and the accounts of Thursday’s rally. None of them states a contract sum for any of the three re-awarded sections. None gives a completion date. None says how much of each section has been built.
That matters for anyone weighing the promise. A flag-off, a speech and a campaign rally are not the same as a finished road. Without a published price or deadline, road users in Ekpoma, Irrua, Auchi and Benin have no fixed yardstick for judging whether the work is on time or on budget.
Each section has its own contractor, so progress can differ along the route. Figures given section by section would let travellers see which part is moving and which is not.
Who uses this road
The highway is the main link between Benin City and the north of Edo State. It passes Ekpoma, home of Ambrose Alli University, and Auchi, home of Auchi Polytechnic. Beyond Okene, it carries traffic towards Lokoja and Abuja. Students, traders, transporters and families travelling between the South-South and the north all depend on it.
What to watch next
- Whether the Federal Executive Council or the Ministry of Works publishes the contract sums for sections II, III and IV.
- A completion date for each section, and any official figure for the work done so far.
- Whether the Benin-Agbor-Sapele road, named at Thursday’s rally, gets its own contract award and timetable.
For more on Edo’s public money, read our report on how Edo State debt costs passed the full-year budget plan by September. We also covered the opening of the Bodo-Bonny road in Rivers State, a federal road that took years to finish, and Edo State’s plan for Edo Air.
Sources: Federal Ministry of Information – Federal Government begins dualisation of key Edo roads (12 Nov 2026) · Federal Ministry of Information – FG flags off dualisation of Ajaokuta Junction-Okene-Okpella-Auchi-Ekpoma-Benin road (20 Feb 2025) · Federal Ministry of Information – flag-off report from Ekpoma (19 Feb 2025) · Nigerian Tribune – FG begins dualisation of Benin-Ekpoma, Auchi, Okpella roads · P.M. News – Okpebholo at 2: Tinubu promises Edo more roads · Nairametrics – FG flags off dualisation on three re-awarded sections · Arise News – Ekpoma flag-off report