The Kaduna-Kano rail line will be inaugurated on Thursday, 3 December 2026, the All Progressives Congress (APC) Presidential Campaign Council said on Sunday. The sections named for that day start at Jaji, north of Kaduna city, and run to Kano. The short stretch that would join them to the existing Abuja-Kaduna line was still held up by land claims in Kaduna metropolis at the last official inspection in October.
Why it matters: until that Kaduna link is finished, no train can run straight from Abuja to Kano, which is the main promise of the 203-kilometre project.
Key facts at a glance
- The APC campaign council set 3 December 2026 for the inauguration, in a statement signed by its spokesperson, Dele Alake, on 8 November.
- Two sections are listed: the 190 km Jaji-Kano stretch of the Kaduna-Kano line and the 250 km Dawanu-Kano-Kazaure-Daura-Katsina stretch of the Kano-Maradi line.
- The Federal Ministry of Transportation put the Kaduna-Kano project at about 90% complete on 23 October.
- The ministry named outstanding land and compensation claims in Kaduna metropolis as the main obstacle to the final connection.
- The campaign put the Kano-Katsina-Maradi line at 70% complete. The ministry said in August that the Kano-Katsina section had passed 75%.

What did the APC campaign council say about the Kaduna-Kano rail?
The statement, reported by Channels Television, The Sun and Legit.ng, said President Bola Tinubu was speeding up two northern rail projects.
It said the Kaduna-Kano line was less than 30% complete when the administration took office in 2023 and now stands at about 90%. It put the Kano-Katsina-Maradi line at 70%, up from about 5% in 2023.
The council also said the President had directed that all outstanding land acquisition and compensation issues within Kaduna metropolis be resolved immediately.
The date came from a party campaign body, not from the Ministry of Transportation or the Nigerian Railway Corporation (NRC). The ministry’s latest public statement on the project, dated 23 October, gave no inauguration date.
What is missing from the 3 December Kaduna-Kano rail plan?
The Kaduna-Kano line is meant to extend the Abuja-Kaduna standard gauge railway (the modern, wider track used on Nigeria’s new lines) so that trains can run from Abuja through Kaduna and Zaria to Kano.
The campaign listed only the Jaji-Kano section, 190 km of the 203 km route. That leaves about 13 km outside the 3 December plan, by De Auditor Space’s calculation. In its 23 October statement, the ministry said its permanent secretary, Funso Adebiyi, identified land claims within Kaduna metropolis as the major obstacle delaying the link between Jaji and the Abuja-Kaduna corridor.
Adebiyi said the inspected stretch covered about 145 km, with only about 10 km of work left on it. He promised the land issue would get immediate attention once his team returned to Abuja.
Habiba Buhari, the ministry’s Director of Rail Transport Services, said the team checked track geometry, drainage and concrete works. “We just want to finalise and test-run,” she said, according to the ministry.
Why do the Kano-Katsina completion figures differ?
The campaign’s 70% figure is lower than the ministry’s own August numbers. After a site inspection from 25 to 27 August, the ministry said work on the 284 km Kano-Katsina section had passed 75%. At the same inspection, Buhari put progress at around 80%, Blueprint reported.
The gap may come from what each figure covers. The campaign measured the whole line to Maradi in Niger Republic, which it described as 400 km long. The contractor, Mota-Engil Nigeria, said in August that the Katsina-Maradi extension is expected by the end of 2027, so that part is far from done.
Who is paying for the northern rail lines?
For the Kano-Katsina-Maradi line, the Finance Ministry said in August that the Federal Government had released its 15% counterpart contribution, with the other 85% covered by external financing. A Development Bank of Southern Africa official said the bank had invested about $250 million, The Business Times reported.
The Abuja-Kaduna line it will connect to cost $876 million, of which $500 million came as a loan from the Export-Import Bank of China, according to public records of the project.
Background: timeline
- 26 July 2016: the 187 km Abuja-Kaduna standard gauge line is formally opened.
- May 2023: Kaduna-Kano is under 30% complete and Kano-Katsina-Maradi about 5%, according to the APC campaign council.
- 25-27 August 2026: a ministry inspection puts Kano-Katsina past 75% and keeps a December 2026 target. Officials cite insecurity, vandalism and land disputes as causes of delay.
- 23 October 2026: the ministry says Kaduna-Kano is about 90% complete and names Kaduna land claims as the main obstacle.
- 8 November 2026: the campaign council fixes 3 December for inaugurating the Jaji-Kano and Dawanu-Katsina sections.
What it means for you
Traders and travellers between Kano, Zaria and Katsina could get a rail option once trains begin carrying passengers. Neither the campaign nor the ministry has announced when passenger services will start, or the fares.
The sections listed for 3 December do not include the Kaduna link. A through journey by train from Abuja to Kano depends on that work, which has no published completion date.
In August, Buhari said land and security problems on the Kano-Katsina route would slow work but not end it. “These will only cause delays, not stop the project,” she said, Blueprint reported.
What happens next
The inauguration is set for 3 December, 25 days from the announcement. Rolling stock (the trains and coaches) is the next major milestone for the Kano-Katsina section, officials said in August. The Katsina-Maradi extension is due by the end of 2027.
Related coverage
- Ibom Deep Seaport: Tinubu approves port first cleared in 2015
- Uyo airport: Tinubu inaugurates new international terminal
- Kano defections: Tinubu meets Ganduje and Badaru
This article is for information only and is not financial advice.
Sources: Channels TV: APC campaign statement · The Sun: Kaduna-Kano rail December 3 · Legit.ng: inauguration date · Federal Ministry of Information: Kaduna-Kano at 90% · Blueprint: Kano-Katsina target · Nigerian Pilot: Kano-Katsina inspection · The Business Times: 75% completion · Wikipedia: Lagos-Kano Standard Gauge Railway


Join the conversation
Comments are moderated. Keep it respectful and on topic: no insults, hate, spam or personal details.